Using REBEL® Sensors for Payment When Breaks Fail
.png?width=1037&height=768&name=465_sensors_small%20(Medium).png)
Industry
Concrete Construction
Challenge
The contractor relied on 42-day core samples for payment, when paving California I-10.
Results
28-day cylinder was only 5K psi. REBEL® Sensors showed that concrete reached final strength at 30 days instead of 42 days.
Key Product
REBEL® Sensors
$2M
Project
$6,575
10% interest saved
$1,100
REBEL® Sensors + Datalogger Cost
$5657
Total Savings for 12 days
About the Project
The contractor relied on 42-day core samples for payment
Paving California I-10
56-day Target Strength = 5.5K psi
3 REBEL® Sensors placed in concrete
Cylinders taken at 1, 4, 7, 14, 28 and 42 days
The REBEL System was deployed, and real-time strength data was provided to prove the results were acceptable and that the concrete in the paving project reached final strength at 30 days.
The Results
28-day Clylinder was only = 5K PSI
REBEL® Sensor Data Real-Time Strength 30-day = 5.5K psi
Final Strength = Payment